2023 Paving Unpaved Streets - 2023049

This project consists of the construction of approximately 1,500 cubic yards of roadway excavation, 7,200 square yards of preparation of untreated roadway, 2,500 linear feet of sawcutting flexible pavement, 7,200 square yards of HMA CL ½ in. 3 inch thick, 21 each cleaning existing drainage structure, 920 square yards of hydroseeding, 50 square yards of cement concrete sidewalk, 155 linear feet of cement concrete curb, sundry utility adjustments, and other related miscellaneous items.