Sunset Hwy (US2) Bicycle Facilities/Shared Use Path - 2024073

Status

Accepting Bids

Bid Date 11/24/25 1:00pm

Company & Contacts

City of Spokane Engineering Dept.
Ben Ward  
(509) 625-6700

Location

Spokane, WA

This site is for the “General Public” to review projects currently out to bid. If you are a Bidder {Prime, Sub or a Supplier} click “Bidders Access” for the portal for Bidders.


This project consists of the construction of approximately 10,000 linear feet of HMA shared use path (12,000 square yards of 3-inch thick HMA and 4-inch thick CSTC), 2700 cubic yards of excavation and embankment, 200 linear feet of storm sewer, 4 drainage structures, 1 20-ft long contractor designed buried structure, 350 linear feet of absorption trench, 400 linear feet of gravity block wall (2.5-4.0 feet tall), 1 pedestrian hybrid beacon system, 100 linear feet of sidewalk, 400 linear feet of cement concrete curb, sundry utility adjustments, and other related miscellaneous items.